Tolt River Riparian Area Restoration
|
Seattle City Light; Tolt River Riparian Area Restoration (#09-1263)
Attachment #78828, Tolt RM 3.7_4.2 creek invasives
|
|
|
|
|     Funding |
  |
|
|
|     Links |
|
|   |
|
|
Seattle City Light (SCL), in partnership with the Stilly Snohomish Fisheries Enhancement Task Force (TF), will control non-native species in 3-acres of riparian property along the Tolt River. This area will then be replanted with native conifers, hardwoods, and shrubs that are currently represented in the vicinity. A 3-acre work area has been identified on portions of three SCL properties, located at approximately Tolt RM 3.7-4.2 and 4.89-5. Within this work area, non-native vegetation is present at varying densities ranging from medium to monoculture. Himalayan blackberry is the primary species of infestation. SCL proposes that within the 3-acre work area, all non-native vegetation will be treated annually for 3 years and will be planted with native vegetation after 1-2 years of treatment. SCL purchased these properties as part of its ESA Early Action Program with the intent to purchase salmonid habitat and protect and restore the habitat as needed. The parcels are located on the lower Tolt River in the San Souci Area where King County is also actively pursuing purchases for salmonid habitat protection and restoration of river processes.
|
|
General Area:
|
|
The project is located on the mainstem Tolt River, on portions of properties located at RM 3.7-4.2 and 4.8-5.0. One section of the project is located on a small tributary creek.
|
|
Waterbody:
|
|
Snoqualmie River, Tolt River
|
|
County:
|
|
King
|
|
Legislative District:
|
|
12
|
|
Congressional District 2022:
|
|
08
|
|
Salmon Recovery Regions:
|
|
Puget Sound
|
|
Watershed Administrative Unit:
|
|
Tolt
|
|
HUC8:
|
|
Snoqualmie (17110010)
|
|
WRIA:
|
|
Snohomish
|
|
Sections:
|
|
11
|
|
Township:
|
|
T25NR07E
|
|
Coordinates:
|
|
47.66043708 -121.87008713
|
|
|
| Worksite Name | Scope of Work | Actual Restoration Cost |
|
Tolt RM 3.7-4.2 and 4.89-5 (#1)
|
Architectural & Engineering (A&E), Other restoration activities, Planting (C.5.c.1), Riparian Plant removal / control (C.5.h.1)
|
$74,300
|
| | Total | $74,300 |
Amounts may not be complete
| Worksite Name | | Property Name | Landowner Type |
|
Tolt RM 3.7-4.2 and 4.89-5 (#1)
|
|
Property 1 - Tolt RM 3.7-4.2 and 4.89-5
|
Local Government
|
| | | | Total |
Amounts may not be complete
| | Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Riparian Habitat Project |
| Planting (C.5.c.1) |
|
|
Acres Planted in riparian (C.5.c.3)
|
3.1
|
| Riparian Plant removal / control (C.5.h.1) |
|
|
Acres of riparian treated for plant removal/control (C.5.h.3)
|
8.0
|
| Milestone Name | Target Date | Description |
|
Project Start
|
12/11/2009
|
|
|
Cultural Resources Complete
|
03/01/2010
|
|
|
Construction Started
|
03/01/2010
|
|
|
Progress Report Due
|
05/31/2010
|
|
|
Annual Project Billing Due
|
07/31/2010
|
|
|
Progress Report Due
|
10/31/2010
|
|
|
A&E Plans Submitted
|
03/31/2011
|
|
|
Progress Report Due
|
05/31/2011
|
|
|
Annual Project Billing Due
|
07/31/2011
|
|
|
Progress Report Due
|
10/31/2011
|
|
|
Progress Report Due
|
05/31/2012
|
|
|
Progress Report Due
|
10/31/2012
|
|
|
Annual Project Billing Due
|
11/15/2012
|
|
|
Progress Report Due
|
05/31/2013
|
|
|
Progress Report Due
|
10/31/2013
|
|
|
Construction Complete
|
03/30/2014
|
|
|
Agreement End Date
|
03/30/2014
|
|
|
Monitoring Complete
|
03/30/2014
|
Work to continue outside grant funding
|
|
Monitor/Steward Plan Submitted
|
05/31/2014
|
|
|
Final Docs/Billing to Mgmt Agy
|
05/31/2014
|
|