Barkley Irrigation Company: Under Pressure
|
Trout Unlimited Inc.; Barkley Irrigation Company: Under Pressure (#14-1737)
Attachment #202403, Barkely_wing_dam_river_during_construction_2011_2
|
|
|
|
|     Funding |
  |
|
|
|     Links |
|
|   |
|
|
|
The objective of this project is to eliminate mortality of listed species in the mainstem Methow and Barkley Diversion side-channel caused by annual excavation of the river bed to create a push up dam for irrigators on the Barkley ditch. The project will improve survival of ESA listed juvenile spring Chinook, steelhead, and bull trout, and also Pacific lamprey and west slope cutthroat trout by eliminating stranding that occurs annually the upper 1/2 mile of the Barkley ditch upstream of the fish screen. Trout Unlimited (TU) and partners the Barkley Irrigation Company (Barkley/BIC), the Methow Conservancy (MC) and the Bureau of Reclamation (Reclamation) will accomplish this by building a permanent pressurized system approximately 2 miles downstream of the current diversion to serve all Barkley users. The perpetual water saving from this project is 26 cfs. The project will eliminate the need for a push-up dam, while not a barrier to fish passage, destroys instream habitat and degrades water quality.
|
|
General Area:
|
|
Middle Methow River, between Winthrop and Twisp
|
|
County:
|
|
Okanogan
|
|
Legislative District:
|
|
07
|
|
Congressional District 2022:
|
|
04
|
|
Salmon Recovery Regions:
|
|
Upper Columbia River
|
|
Watershed Administrative Unit:
|
|
Middle Methow River
|
|
HUC8:
|
|
Methow (17020008)
|
|
WRIA:
|
|
Methow
|
|
Sections:
|
|
24
|
|
Township:
|
|
T34NR21E
|
|
Coordinates:
|
|
48.43807469 -120.15429452
|
|
|
| Worksite Name | Scope of Work | Actual Restoration Cost |
|
MVID Diversion (#1)
|
Architectural & Engineering (A&E), Irrigation practice improvement (C.3.e.1), Obtain permits
|
$2,593,843
|
| | Total | $2,593,843 |
Amounts may not be complete
| Worksite Name | | Property Name | Landowner Type |
|
MVID Diversion (#1)
|
|
Property 1 - MVID
|
Private
|
| | | | Total |
Amounts may not be complete
| | Category / Work Type / Metric | Final |
Restoration Metrics (rolled up from Worksite level) |
Instream Flow Project |
| Irrigation practice improvement (C.3.e.1) |
|
|
Acre Feet Of Water Conserved (C.3.e.2)
|
2342
|
|
|
Cfs (Cubic Feet Per Second) Of Water Conserved (C.3.e.3)
|
26
|
Permits |
| Obtain permits |
|
|
Number of permits required for implementation of project
|
8
|
| Milestone Name | Target Date | Description |
|
Project Start
|
12/05/2014
|
|
|
Preliminary Design to RCO
|
05/20/2015
|
|
|
Progress Report Due
|
06/15/2015
|
|
|
Applied for Permits
|
06/30/2015
|
|
|
Annual Project Billing Due
|
07/31/2015
|
|
|
Cultural Resources Complete
|
08/15/2015
|
|
|
Progress Report Due
|
12/15/2015
|
|
|
Progress Report Due
|
06/15/2016
|
|
|
Annual Project Billing Due
|
07/31/2016
|
|
|
Permits Complete
|
08/01/2016
|
|
|
Progress Report Due
|
12/15/2016
|
|
|
Progress Report Due
|
06/30/2017
|
|
|
Annual Project Billing Due
|
07/31/2017
|
|
|
Progress Report Due
|
12/29/2017
|
|
|
Annual Project Billing Due
|
07/31/2018
|
|
|
Landowner Agreement to RCO
|
08/03/2018
|
|
|
Final Design to RCO
|
08/03/2018
|
|
|
Progress Report Due
|
08/03/2018
|
|
|
Restoration Started
|
09/04/2018
|
|
|
Bid Awarded/Contractor Hired
|
12/31/2018
|
|
|
Progress Report Due
|
09/30/2019
|
|
|
Annual Project Billing Due
|
09/30/2019
|
|
|
Final Billing Due
|
03/30/2020
|
|
|
RCO Final Inspection
|
03/31/2020
|
|
|
Restoration Complete
|
03/31/2020
|
|
|
Final Report Due
|
03/31/2020
|
|
|
Agreement End Date
|
03/31/2020
|
|